Customer:
Private Garden Project (Audit commissioned by Lucky International/Sioen India)
Project Category:
Audit, Rectification & Authorized Installation Services
Customer Requirement:
The client and the distributor required a professional intervention to resolve a "failed project" scenario. Key requirements included: Forensic Inspection: Identifying why a one-year-old fabric was tearing. Warranty Verification: Determining if the failure was a material defect or an installation error. Structural Rectification: Strengthening the existing "estimated" steel frame to handle actual wind loads. Professional Re-Installation: Ensuring the new membrane was wrinkle-free and tensioned correctly to qualify for a genuine Sioen warranty. Expert Reporting: Providing a detailed technical report to the national distributor.
Project Result:
Successfully conducted a technical forensic audit of a failed third-party installation. Following the audit, FV INFRA LLP was commissioned to rectify and re-install the membrane structure, restoring the project's structural integrity and ensuring it met international warranty standards.
What we did:
Technical Audit: Conducted a site-wide inspection of fittings, steel sections, and tensioning levels. Expert Reporting: Provided a documented verdict proving that poor installation (loose fittings and no engineering logic) was the cause of failure. Engineering Reinforcement: Corrected the steel structure based on qualified structural drawings to ensure it could withstand Amravati’s wind speeds. Authorized Installation: Applied our specialized patterning and tensioning techniques to install the new Sioen fabric, ensuring it acts as a rigid, durable membrane rather than a loose cover. Hardware Upgrade: Replaced all low-grade accessories with industrial-strength, rust-proof components.
Project Description
FV INFRA LLP was appointed by Lucky International (Sioen India's primary distributor) to investigate a premature fabric failure in Amravati. Our technical audit revealed that the inverted conical tensile canopy failed due to poor workmanship, lack of proper tensioning, and sub-standard hardware used by a non-authorized vendor. As a leading tensile shed manufacturer in Amravati and an authorized partner, we were entrusted to rectify the site. We reinforced the steel framework, replaced rusted accessories with high-grade hardware, and professionally re-tensioned the Sioen membrane according to strict engineering protocols.
Project Budget:
High
Completion Date:
2025-11-20T00:00:00